You have two letters of intent on your desk. One is for a suite on the 20th floor of a Brickell tower. The other is for a bay in a converted Wynwood warehouse. The square footage is close. The rent math clearly favors one of them.
What neither lease tells you is what it will cost to build out the space, or how long it will take before you can open. Nothing in either document mentions freight elevator hours, whether the building has enough electrical service for your plan, or which permitting office will review your drawings.
Those details can swing your buildout budget and schedule more than the finishes you pick. We’ve built across Miami for more than 25 years, and our own office sits off NW 36th Street on the Doral side of town. Brickell, Wynwood, and Doral make a useful comparison because each one sits at a different point on the three things that drive a buildout. Once you see how they differ, you can evaluate any space in Miami the same way.
Three Things Your Neighborhood Decides Before Construction Starts
Before a single wall goes up, your location has already decided three things for you.
Who reviews your permit. Miami-Dade isn’t one permitting office. Each municipality runs its own building department with its own reviewers, comment cycles, and turnaround times. We covered this in detail in Miami’s Permit Office Reality. The short version: where your project sits changes how long approval takes, and most delays start with an incomplete submission, not the permit office.
What kind of building you’re working in. A managed high-rise, a 1950s warehouse, and a newer flex building each come with a different set of existing conditions, rules, and surprises.
How hard it is to physically build. Where do trucks unload? Where do materials get stored? When are crews allowed to work? Logistics rarely show up in a lease, but they show up in your contractor’s price and schedule.
Keep those three in mind as we go through each neighborhood.
Brickell: The Building Sets the Rules
Brickell projects go through the City of Miami’s building department. But in Brickell, the permit office usually isn’t the biggest variable. The building is.
Most office space in Brickell sits in managed high-rise towers, and every one of those towers has its own construction rules. Expect some version of the following:
- Freight elevator time has to be reserved, and you may be sharing it with other tenants’ contractors and move-ins.
- The loading dock runs on scheduled windows, so deliveries have to be timed to them.
- Noisy or odorous work, like core drilling or demolition, is often limited to nights or weekends so it doesn’t disturb occupied floors.
- Common areas have to be protected, and your contractor has to carry the insurance certificates the building requires.
- The landlord reviews and approves your drawings before you submit for permit, which adds a step to the schedule.
Each of these adds cost. After-hours work means premium labor rates. Slower material movement means more crew hours. Landlord review time stacks on top of permit review time. None of it is unusual, but all of it should be in your budget and schedule from day one. We go deeper on this in the logistics of office build-outs in high-rise buildings.
The question to ask before you sign: Can I get a copy of the building’s construction rules and tenant work letter? Hand it to your contractor before you commit.
Wynwood: Older Bones, Newer Rules
Wynwood is also in the City of Miami, but it sits inside the Wynwood Neighborhood Revitalization District, known as NRD-1. That overlay layers extra rules on top of the city’s Miami 21 zoning code.
For new construction, NRD-1 changes a few things. After a 2022 update, all new buildings in the district must go before the Wynwood Design Review Committee. Buildings up to 20,000 square feet can qualify for a 100% parking reduction, and on-street parking can’t be counted toward minimum parking requirements, according to Bilzin Sumberg’s summary of the changes.
If you’re doing an interior buildout in an existing building, those rules mostly won’t apply to you. Your risk lies elsewhere: in the building itself. A lot of Wynwood’s space is older low-rise industrial stock that was converted for office, retail, and restaurant use. Before you sign, have a contractor walk the space and check:
- Whether the electrical service can carry your planned load, or whether you’ll need an upgrade
- The fire sprinkler and fire alarm systems, and whether they’ll need to be extended or brought up to current code for your use
- Restrooms, and whether they meet accessibility requirements for your occupancy
- The roof and building envelope, since a leak over a finished office is a bigger problem than a leak over a warehouse
- The HVAC system, which may have been sized for storage rather than people
Logistics are their own challenge in Wynwood. The streets are tighter, staging space is limited, and event-heavy weekends bring crowds. Your contractor needs a plan for where materials go and when they arrive. For the new-construction side of the neighborhood, see our guide to Class A office construction in Wynwood.
The question to ask before you sign: Has anyone checked the electrical capacity, fire protection, restrooms, and roof for the use I’m planning?
Doral: Room to Work, Different Questions
Doral is its own city, in more ways than one. Projects there go through the City of Doral Building Department, not the City of Miami or unincorporated Miami-Dade. That means different reviewers, a different submission process, and different turnaround times. Don’t assume a schedule that worked in Brickell will hold in Doral, or the other way around.
Physically, Doral is often the easiest of the three to build in. Much of the office, flex, and warehouse space is newer, low-rise, and surrounded by surface parking. Trucks can pull up. Materials can be staged on site. There are usually fewer restrictions on working hours than in an occupied tower.
The watch items in Doral are different:
- Change of use. Converting warehouse or flex space into office or showroom space can change the occupancy classification, which affects exits, fire protection, restrooms, and more.
- Warehouse shells. Open warehouse space often needs new ceilings, HVAC sized for people, and lighting before it works as an office.
- Exterior openings. New storefronts or windows need impact-rated products, which carry their own cost and lead times.
Our guide to Class A office construction in Doral has more on building in the area.
The question to ask before you sign: Does my planned use match the building’s current occupancy classification, or am I triggering a change of use?
A Side-by-Side You Can Use
Here’s the comparison in one place.
- Brickell: Permits go through the City of Miami. The typical space is in a managed high-rise tower. The biggest cost risk is after-hours work and slower material movement. The biggest schedule risk is landlord review stacked on permit review.
- Wynwood: Permits go through the City of Miami, with NRD-1 rules on new buildings. The typical space is a converted low-rise industrial building. The biggest cost risk is hidden existing conditions like electrical, fire protection, and roofing. The biggest schedule risk is discovering those conditions after the lease is signed.
- Doral: Permits go through the City of Doral. The typical space is newer low-rise office, flex, or warehouse. The biggest cost risk is converting warehouse space into office use. The biggest schedule risk is a change of use you didn’t plan for.
The same three questions work anywhere in Miami: Who reviews my permit? What building am I in, and what condition is it in? How do materials and crews get to my space? If you can answer those before you sign, you’re far ahead of most tenants. For a broader checklist, see what to look for from a buildability standpoint in your office search.
The Bottom Line
Go back to those two letters of intent. The better deal is the one where the rent and the buildout both make sense, and you can’t know that from the lease alone. A cheaper Wynwood bay with an undersized electrical service can end up costing more than a Brickell suite. A Brickell suite with strict after-hours rules can take longer to open than a Doral flex space that needs a full buildout.
Before you sign, have someone who builds in all three neighborhoods walk the space with you. We’ll tell you what the lease doesn’t. Reach out to our team or learn more about our consultation services.
Frequently Asked Questions
How long does an office buildout take in Miami?
It depends on the size of the space, the permitting jurisdiction, the building type, and how complete your drawings are when they’re submitted. We break down typical timelines in How Long Does an Office Buildout Take in Miami?
Is Doral part of the City of Miami for permitting?
No. Doral is its own city with its own building department. Its review process and turnaround times are separate from the City of Miami, which handles permits for Brickell and Wynwood.
Do I need Wynwood Design Review Committee approval for an interior buildout?
Under the 2022 NRD-1 updates, Wynwood Design Review Committee review applies to new buildings in the district. An interior tenant buildout generally goes through standard City of Miami permitting. Confirm with the city for your specific scope, especially if you’re changing the exterior.